Rail Wheel Plant Project (RWP/Bela)

Chhapra - Setting up of Wheel Manufacturing Plant

SN

Project Parameter

Status/ Remarks

1

Pink Book Item 

Original: 220/05-06/NER; Current: 18-19/RWP

2

Sanctioned Cost

Rs. 1417.23 crore (RE-3 with material modification and re-appropriation)

3

 Location

Vill.–Bela (nearest Rly. Station Nayagaon 6 km away), Block – Dariyapur, District HQ – Chhapra, District – Saran, Bihar.

4

Outlay in year 18-19

Rs.47.12 cr. (PH-42).

5

Cumulative Exp. upto last FY (17-18)

Rs.1364.20 crore (PH-42). 

6

Total exp. upto end of Apr’18 (FY 18-19)

Rs. 7.32 crore

7

Cumulative Exp. upto Apr’18

Rs. 1371.52 crore

8

 Target

June, 2019.

9

 Consultancy

M/s RITES were awarded consultancy contract for detailed layout, detailed structural design and GFC drawings, Electrical and telecom cables routes. Work has been completed.

10

Land

  1. Workshop - 198 acres (includes 36 acres of Rail / Road connectivity land).
  2. Colony -   95 acres.
    Total - 293 acres.
  3.  Total cost of Land = Rs.24.32 crore.

11

Electrical Load

Electrical supply-132/11 KV (Twin Incomer from Sitalpur Grid & Vaishali Grid), Total connected load – 60 MVA,
Maximum load – 27 MVA.

12

Capacity

1 lakh BOXN wheel discs per annum.

13

Scope of work

Workshop comprising of Melt Shop(MS), Mould Room,(MR), Wheel Final Processing Shop(WFPS), Plant Care Shop (PCS), Road Transport Shop (RTS), Mould Repair Shop (MRS) and Utility Shop

Officers Colony (40 Qtrs.), Staff Colony (541 Qtrs.).

14

Project completion status

  1. Physical Progress- 98%.
  2. Financial Progress- 96.78%.
  3. All Civil, Electrical and Mechanical works of Workshop area have been completed and handed over.
  4. Keys of all 40 nos. Officer’s quarters have been handed over to RWP/Bela authorities for further allotment at their end.
  5. Staff Colony (Phase-I) - in progress (PDC- Sep’ 18).
  6. Tender for 184 units type-II staff quarters (Phase-II) has been floated on 10/01/2018 and technical bid opened on 26/02/2018. Briefing note vetted. Credential under verification.

 



Source : CMS Team Last Reviewed on: 01-06-2018  

  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy

© 2017  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.