Harnaut - Setting up of workshop to undertake periodical overhauling of up to 50 coaches

Carriage Repair Workshop Project, Harnaut

SN

Project Parameter

Status /Remarks

1

Pink Book Item 

Original:  340/2003-04/ECR.

2

Sanctioned Cost

  1. Abstract Estimate : Rs.98.74 crores (Sanctioned in FWP 2003-04 item n.o.340/ECR)
  2. Revised Estimate (RE-1) - Rs.328.37 crore.

3

 Location

Harnaut (next to Bakhtiyarpur station - distance 8 km) District – Nalanda on Bakhtiyarpur - Rajgir (Tilaiya) Rly line of Danapur Division, ECR. 

4

Outlay in year 17-18

Rs.11.78 crore (PH-42 CAP).

5

Exp upto Mar’ 18 in year 17-18

Rs.4.12 crore (approx.) – PH-42

6

Cumulative Exp. Upto Mar'18

Rs.334.66 crore (101.92%) – PH-42

7

 Target

March, 2018.

8

 Consultancy

M/s RITES were awarded consultancy contract at a total cost of Rs.1.1 crore for planning, preparation of detailed estimate, detailed design, detailed drawings and preparation of tender documents for Civil, Electrical, S&T and IT portions for workshop only.

9

Land

  1. Total  -120 acres (Workshop -83 acres, Colony - 37 acres)
  2. Total cost of Land  -    Rs. 21.24 crores

10

Electrical Load

Electrical supply – 33/11KV,

Total connected load – 7.8 MVA,

Maximum demand – 5 MVA

11

Capacity

POH of 600 Non-AC ICF design Coaches per annum.

12

Scope of work

Carriage Repair Workshop comprising of Carriage Repair Shop (220mx30m), Bogie Repair Shop (100mx15m), Sheet Metal Shop (75mx25m), Roller Bearing Shop (20mx60m), Wheel Shop (60mx20m), Paint Shop (160mx20m), Outgoing Shop(80mx15m) and Officers Colony (14 Qtrs) & Staff Colony (380 Qtrs.)

13

Project completion status

  1. The workshop has been completed and handed over to East Central Railway in 12.06.2012.
  2. All works pertaining to Officers and Staff Colony have been completed &handed over.
  3. Physical Progress- 100%.
  4. Financial Progress- 100%.
  5. Completion report has been accepted by CAO/WP on 28.03.2018. This project is now complete and closed.

 



Source : CMS Team Last Reviewed on: 09-07-2018  

  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy

© 2017  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.