Kurnool - Setting up facilities for coach midlife rehabilitation workshop

Coach Midlife Rehabilitation Workshop Projects, Kurnool

(Capacity - 250 Coaches per year)

S.N

Project Parameter

Status/Remarks

1

Pink Book Item 

Original : 579/13-14/SCR, Current : 643/18-19/SCR.

2

Sanctioned Cost

Rs. 110 crores (Abstract).
Detailed estimate has been sanctioned at a total cost of Rs. 283.26 Crore.

3

 Location

Kurnool City Station is on Gadwal-Dhone section of HYD Division of S.C. Railway (Location between Alampur & Kurnool City Railway stations of HYB Div./SCR between Kms 239/1 to 238/2), District – Kurnool (Andhra Pradesh).

4

Outlay in year 18-19

Rs.58.17 crore (PH-42).

5

Cumulative Exp. upto Aug'18

Rs.42.82 crore

6

 Target

June, 2019

7

 Consultancy

Nil

8

Land

124 acres of land has been handed over by Kurnool district administration.17.95 acres land received in Telangana & permission for 4.0 acres are taken from Wakf Board and Endowment Boards.

9

Electrical Load

Electrical supply – 11KV /415V
Total connected load –  6 MVA (estimated)
Maximum demand –   2MVA (estimated)

10

Capacity

250 Coaches per year (MLR).

11

Scope of work

Washing Shed (30x20m), Lifting Shop (30x21.5m), Stripping Shop (90x20m), Body Repair Shop (141x30), Paint Shop (170x10), Paint Booth + Oven Shop (130x10m), Furnishing Shop (170x20m), Final Shop (30x43.5m) and Colony (Approx. 30.56 acre).

12

Project completion status

  1. Physical Progress- 11%.
  2. Financial Progress-15.12%.
  3. Earthwork Tender- Work will be completed by Sep’ 18.
  4. Composite Tender- Contract for composite work for a total value of Rs.232.94 crore awarded to M/s HYT-SAM India (JV), Delhi on 13.10.2017. PDC – April’19. 
  5. Finalisation of design drawing with executing agency under process. GAD drawings of 26 shops are approved. GAD drawings of 26 shops are approved.GAD for 5 buildings have also been finalised.
  6. Piling work at the site for the Bogie shop area has started.

 



Source : CMS Team Last Reviewed on: 07-09-2018  

  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy

© 2017  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.